GPU TDP vs facility power
A worked example and the assumptions to document.
Explore resource →Build an explicit chain from equipment inputs to IT demand, facility overhead and capacity assumptions.
Calculations run in your browser. Sharing puts numeric assumptions in the link. No registration required.
Use whole-server data or measurements where possible. If using chip power, explicitly add the rest of the system; do not call that value a complete server rating.
Carry inputs forward: use “Use IT load in capacity planner” below the calculator, then review and apply the IT MW and PUE on the next page. Other planning assumptions are preserved. You can also enter these values manually.
Continue to capacity sandbox →A worked example and the assumptions to document.
Explore resource →Different uses for an energy ratio and a scenario multiplier.
Explore resource →Use load fraction and your tariff, without invented market prices.